|
| Dan Caputo, MIP Operations Manager for Vironex, works
inside the MIP support vehicle which is equipped with the
MIP system, FC5000 Field Instrument, detectors, and large
output display. |
MIP Project Summary: Vironex
Vironex was retained to define the extent of vertical TCE
contamination in a downgradient plume. The objective was to
determine if TCE (expected at 100 ug/L) was located above weathered
bedrock or if it had migrated into it.
As a result of the MIP detections, the injection strategy for the
site included packer isolation of the weathered bedrock and highpressure
injection of potassium permanganate into the fractures to
chemically oxidize the TCE. Using the Geoprobe® 6600 equipped
with an augerhead, Vironex advanced 4.25-in. ID augers to 27 feet.
 |
| This MIP log demonstrates that TCE was detected by the ECD detector both at the
bedrock interface (2.1 x 105 at 27 feet bgs) and 10 feet into the weathered bedrock
(2.6 x 105 at 37 feet bgs). |
The augers were left in place as a conductor to prevent cave-in of
the alluvium. The Macro-Core® soil sampler was
then used to further advance the boring below the
auger bit. Once the boring was cored to 40 feet, the
inflatable packer was then lowered into the open
boring and inflated at 27 feet.
Vironex uses the MIP to support consultants in
remediation of their client’s sites. Typically, traditional
site characterization does not provide enough vertical detail of contaminant mass distribution which results
in the consultant treating the site uniformly. The MIP allows for continuous recording of VOC mass distribution
in relation to lithology. This provides additional vertical information that allows for a more targeted approach to
delivery of in-situ reagents for chemical oxidation or bioremediation.
“The link between the MIP results and in-situ chemical
injection design is a key driver for the growth of our
MIP services across the U.S.” |
Eliot Cooper, National Director of Remediation Support Services
Vironex • Golden, CO |
The MIP was used at this site since the existing monitoring wells did not provide enough information as to
whether the TCE contamination
existed above or in the weathered bedrock. As can be seen from the MIP log, the TCE
had migrated into the weathered bedrock which required a more complex delivery approach
than just targeting the TCE above the bedrock.
Frank Stolfi, National Director of MIP Services for Vironex, and Dan Caputo, Manager
of MIP Operations for Vironex, both located in Santa Ana, CA, mobilized the custom-built
Vironex MIP Sprinter van and Geoprobe®
6600 machine for the project.
 |
 |
| The Vironex, custom-built MIP Sprinter Van and a Geoprobe® 6600 complete MIP work in Colorado. Working at
the foot of the probe machine is T.J. Haley, Vironex MIP Field Operator. |
(l to r) Richard Freeman, Vironex Injection
Operator, and Mike Martin, Vironex Rocky
Mountain Regional Manager, use a Geoprobe®
6600 to install an inflatable packer to isolate a
section of bedrock at a project site. |
|